Module 4: Subcontractor Coordination

PM for HVAC — Intern Academy

Instructor: S.F. Johnson  |  Duration: 60–90 minutes

Coordinate suppliers and trades so scope fits together without gaps, delays, or surprises. In this module you’ll align scopes, level proposals, lock a communication cadence, control RFIs/COs, and drive quality, safety, and closeout through your subs.

📘 Learning Objectives

  • Prequalify and select the right subs with clear SOW and flow-down terms.
  • Build an interface matrix (HVAC ↔ Electrical, Controls, Insulation, TAB, GC) to eliminate scope gaps.
  • Run a predictable cadence: lookahead, coordination meetings, RFIs/submittals, logistics, and inspections.
  • Manage changes, backcharges, safety/quality gates, and pay apps with documentation that stands up to audit.
  • Close out subs cleanly: as-builts, O&M, training, warranties, attic stock, and lien waivers.
✅ Prequalification & Buyout
  • Prequal: Safety (EMR/OSHA), financials, capacity, past performance, key staff, local presence.
  • Leveling: Normalize proposals (scope, lead times, freight, taxes, warranty, exclusions).
  • Flow-down: Match GC/Owner terms: insurance, indemnity, schedule/liquidated damages, submittal/SOV rules, closeout deliverables.
  • Term Sheet: One page of must-haves (RFI/CO timing, daily reports, QA/QC, safety, documentation standard).
🧩 Scope & Interface Matrix (examples)
Interface Item Responsible Notes/Clarifications
Disconnects & feeders to RTUs/VFDsElectricalHVAC provides nameplate loads; Elec provides feeders & OCPD
DDC controls, sensors, & networkControls SubHVAC provides points list & terminations at equipment
Duct & pipe insulationInsulation SubVerify thickness, jacketing, labeling standard
TAB reports & balancing valvesTAB SubHVAC ensures access; TAB provides preliminary & final reports
Roof curbs & crane/riggingHVAC + GCCurb by HVAC vendor; crane window with GC
Tip: Publish this matrix with the award PO so subs can price gaps before mobilization, not after.
📅 Coordination Cadence
  • Weekly: 3-week lookahead by trade (materials, access, inspections). Update constraints board.
  • MEP/BIM: Clash review; issue coordination notes; lock sleeve/blockout drawings before pours.
  • Field: Daily huddle & safety/JHA; QC spot checks (hang spacing, anchors, slope, labels).
  • Docs: Meeting minutes with owners, assignees, due-by dates; RFI & decision log aging.
📝 RFIs, Changes & Payment
  • RFIs: Use photos & redlines; propose solutions; track business-day aging; link to affected WPs.
  • COs: Require priced proposals within a set window (e.g., 5 days); accept T&M with daily signed tickets.
  • Backcharges: Written notice, photos, timecards, materials, and cause; price per contract (OH/profit rules).
  • Pay Apps: Sub SOV aligns to your prime SOV; conditional/unconditional lien waivers; retainage & closeout deliverables.
📊 Performance Management
  • KPIs: lookahead hit rate, RFI/CO turnaround time, rework %, safety/QA issues, labor productivity vs plan.
  • Recovery: add crew/shifts, resequence, partial releases; document impacts for CO negotiation.
🔚 Sub Closeout Checklist
  • As-builts (redlines to CAD/PDF), O&M manuals, warranties, start-up & training sign-offs.
  • Test reports (TAB, start-up forms, controls trending), attic stock delivered & inventoried.
  • Final pay app with unconditional waiver; warranty start date; punchlist cleared.

🧰 Subcoord Mini Tools

🏅 Sub Prequalification Score

Weights: Safety 30%, Financial 25%, Capacity 20%, Performance 25%

🧮 Scope Gap Quick Check

Heuristic: Risk = Required − Covered + Exclusions

⏳ Submittal/RFI Aging
Due By:
Business Days Elapsed:
💳 Backcharge Builder

Remember: attach notice, photos, time/material proof, and contract references.