Services all contractors need since 2010

Cost Controls & Budget Tracking

Cost Controls & Budget Tracking

Module 3: Cost Controls & Budget Tracking

PM for HVAC — Intern Academy

Instructor: S.F. Johnson  |  Duration: 60–90 minutes

Build a defensible budget baseline, track costs with clear codes, forecast early, and protect margin with tight change control. This module gives you a practical, repeatable framework for weekly cost meetings and month-end reporting.

📘 Learning Objectives

  • Create a budget baseline mapped to cost codes and the Schedule of Values (SOV).
  • Track commitments, accruals, and actuals; separate labor hours from dollars.
  • Use EV (CPI/SPI), cost-to-complete, and EAC methods to forecast finish cost.
  • Run a disciplined change process for scope gaps, allowances, and alternates.
  • Publish a clean monthly WIP with cash-flow forecast and risk notes.
🏗️ Budget Baseline & Cost Codes
  • Baseline: Freeze the awarded estimate by cost code (e.g., 23-07 Duct, 23-21 Piping, 23-72 Equipment, 23-09 Controls, 01-Gen Conditions).
  • SOV: Align SOV divisions to your code rollups. Don’t mix labor/material across unrelated scopes.
  • Buckets: Labor (hrs & $), Material, Subcontract, Equipment/Crane, Freight/Tax, OH, Contingency (held by PM).
Cost Code Desc Budget $ Budget Hrs Committed $ Actual $ (to date)
23-07-101Duct & Fittings$180,0002,100$95,400$41,250
23-72-210RTUs & Curbs$260,000180$248,300$0
23-09-330Controls (DDC)$95,000520$0$12,480
Tip: Track commitments (POs/subcontracts) separately from actuals and use accruals to capture received-not-invoiced at month end.
📅 Weekly & Month-End Cadence
  • Weekly: update commitments, hours, and progress %; refresh ETC by code.
  • Run EV: CPI (cost), SPI (schedule) at project and major-code level.
  • Trend log: risks, pending COs, buyout variance, productivity flags.
  • Month-end: accrue receipts; issue AIA billing (G702/703) & WIP.
  • Forecast: EAC per code using CPI/ETC; refresh cash-flow curve.
  • Review: PM + Superintendent signoff; note corrective actions.
📈 EV & Forecasting Basics
  • EV (Earned Value) = BAC × Physical % Complete
  • PV (Planned Value) = BAC × Planned %
  • CPI = EV ÷ AC   |   SPI = EV ÷ PV
  • EAC (CPI) = BAC ÷ CPI   •   ETC = EAC − AC
  • TCPI = (BAC − EV) ÷ (BAC − AC) → efficiency needed to hit BAC
📝 Change Orders, Allowances & Contingency
  • Keep a CO log with cost, status, margin, and schedule impact; submit early, update often.
  • Track allowances with current balance; move variances to COs when scope solidifies.
  • Hold PM contingency centrally; release via internal transfer with notes.
CO # Description Cost Margin Sell Status
CO-02Add VFD on AHU-2$5,60018%$6,829Submitted
💵 Billing, Retainage & Cash Flow
  • AIA G702/703 progress billing: percent complete per SOV line, minus retainage.
  • Cash flow: forecast monthly billings vs vendor payables; protect working capital.
  • Close the month with accruals (received not yet invoiced) to avoid shock next cycle.

🧰 Cost Control Mini Tools

📈 EV Snapshot & Forecast
👷 Labor Productivity Monitor
💵 Cash-Flow Planner
🧾 CO Margin Builder
🧪 Cost Control QA/QC Checklist
  • Budget baseline locked; changes documented via internal transfer or CO.
  • Every code shows: Budget, Commit, Actual, ETC, EAC, variance.
  • Labor tracked in hours and dollars; weekly productivity reviewed with Super.
  • Pending COs aged > 14 days escalated; allowance balances reported.
  • Month-end accruals posted; WIP ties to GL and AIA billing.

🧠 Quiz Yourself

When you finish this module, take the Module 3 Quiz on ConstructIQ.

Take Quiz