Module 5: Closeout & Documentation
PM for HVAC — Intern Academy
Instructor: S.F. Johnson | Duration: 60–90 minutes
Lock in a clean turnover. This module gives you a checklist-driven approach to documents that close the job: O&Ms, as-builts, training records, warranties, test reports, attic stock logs, lien waivers, and final pay paperwork.
📘 Learning Objectives
- Plan a closeout timeline back-from substantial completion (SC) and turnover (TCO).
- Assemble a compliant turnover package: O&Ms, as-builts, warranties, test reports, attic stock.
- Run punchlist documentation and final inspection sign-offs with traceable evidence.
- Control document versions and approvals with a simple, auditable register.
- Complete final pay: retainage, lien waivers, and closeout affidavits.
- T-60 days: Publish closeout plan; draft O&M index; start as-built clean-up; confirm attic stock list; schedule training windows.
- T-30 days: Issue O&M draft for review; lock labels & asset registry; pre-final inspections; capture punchlist photos.
- T-14 days: Final O&M PDF; as-built package; warranty letters; test reports (startup, TAB, functional if applicable).
- SC/TCO: Turnover binder + USB/cloud; training sign-ins; submit conditional waivers with pay app.
- Final: Unconditional waivers; retainage release; archive package delivered to owner & internal server.
- O&M manuals (PDF) with equipment cutsheets and wiring diagrams
- As-builts (PDF/CAD), valve charts, damper schedules
- Warranty certificates (start dates & terms), startup reports
- Testing reports (TAB; functional tests if required)
- Training agenda, recordings/slide deck, sign-in sheets
- Asset registry (tag, serial, room, panel/VFD associations)
- Attic stock list & receipt, spare filters/belts
- Emergency contacts & seasonal setpoint quick guide
Tip: Deliver digitally (PDF + structured folders) and physically (tabbed binder or QR card set).
- Naming:
JOB-Phase_Discipline_DocType_Version_YYYYMMDD.pdf
- Register fields: Doc ID, Title, Owner, Status (Draft/Review/Approved), Rev, Due-By, Link, Notes.
- Transmittals: Date, recipient, description, revision, action required; store as PDF.
- Distribution: Owner, GC, CxA, Maintenance lead, IT/BMS admin, PM, Superintendent.
Doc ID | Title | Owner | Status | Due-By |
---|---|---|---|---|
CL-OM-01 | O&M Manual – HVAC | PM | Review | 2025-09-15 |
CL-AB-02 | As-Builts – M Sheets | Coord | Draft | 2025-09-10 |
- Capture items with photo + location + trade + priority (A life/safety, B function, C cosmetic).
- Weekly burn-down: planned vs cleared; upload “after” photos for sign-off.
- Final inspections: schedule windows, pre-walk checklists, re-inspection buffer.
- Retainage release conditions: all docs delivered, punchlist closed, waivers submitted.
- Lien waivers: conditional with each pay app; unconditional upon cleared funds.
- Closeout affidavits, warranties, and release of claims with final application.
🧰 Closeout & Documentation Mini Tools
📅 Closeout Back-Plan
O&M Final Draft By: —
As-Builts Ready By: —
Training Materials Ready: —
Waivers/Final Pack Ready: —
✅ Turnover Completeness Meter
—
📚 O&M Index Builder
—
💳 Final Billing Readiness
—
Checklist: waivers, warranties, O&Ms, as-builts, punchlist closure, final inspections.
- All deliverables approved; links live; filenames follow convention.
- Punchlist closed with photo proof; re-walk sign-off obtained.
- Training completed (agenda + sign-ins + slides/video provided).
- Warranties registered; startup/TAB reports filed.
- Final pay app prepared with correct waivers and retainage math.
🧠 Quiz Yourself
When you finish this module, take the Module 5 Quiz on ConstructIQ.