Demo Estimating — Module 2

Reading Plans & Understanding Demolition Scope

Read the drawings like a demolition PM: align demo intent across A/S/M/E/P sheets, isolate keep/protect items, sequence safely, and translate plan notes into takeoff units you can defend.

🎯 Learning Objectives

  • Decode demo symbology, hatches, and keynotes; confirm “what stays” vs “what goes.”
  • Cross-reference demo intent across Architectural, Structural, and MEP demo sheets.
  • Spot structural risks and build a safe, staged removal sequence.
  • Plan disconnects, temp protections, and access/egress with the field in mind.
  • Capture addenda/revisions and prevent scope gaps before pricing.

🧾 Construction Drawings & Demolition Plans

Demo sheets show removal limits via hatches, clouds, and dashed outlines. Treat the legend as law and verify against general notes, keynotes, and sheet indices.

  • Stays vs. Goes: “PIP/Protect in Place” items, heritage finishes, active utilities, egress paths.
  • Legend & Keynotes: Hatch patterns, sawcut lines, infill notes, temporary partitions.
  • Phasing: Colored zones, phase tags, swing spaces, night/occupied constraints.
  • Clouds & Rev triangles: Track addenda and delta changes by sheet.
📌 Cross-check: A-Demo (rooms/partitions) ↔ S-Demo (structure) ↔ M/E/P-Demo (systems). Conflicts become RFIs.

🏗 Identifying Structural Elements to Remove or Preserve

Structural errors are the costliest. Confirm load paths and temporary works before pricing aggressive production.

  • Differentiate non-load partitions vs. shear walls, brace frames, and transfer beams.
  • Look for “DO NOT REMOVE”, shoring notes, and engineered temp support details.
  • Coordinate slab infill thicknesses, rebar dowels, and edge prep in the bid (not as a surprise CO).
  • Plan crane picks, interior equipment access, and weight limits on elevated slabs.
🛠️ Estimator’s Note: Include a line for engineered shoring or qualify as an allowance with unit pricing.

🔌 Reviewing MEP Disconnection Plans

Price legal, safe disconnects up front—don’t bury them in production rates.

  • Electrical: panel lockout, feeder isolation, lighting controls, fire alarm devices.
  • Mechanical: duct caps, gas capping, RTU/condensing unit recovery, refrigerant handling.
  • Plumbing: cap domestic, sanitary, storm; water heater/tank removal; trap sealing.
  • Fire/Life Safety: sprinkler impairments, F/A bypass plans, hot work permits.
⚠️ Coordinate with licensed trades. Document “by demo” vs “by others” in a disconnect matrix.

🕵️ Site Investigation & Pre-Demolition Surveys

  • Measure actual wall types, slab thickness, roof layers; verify existing vs. as-builts.
  • Access & haul paths, laydown, crane/picker positions, street permits.
  • Hidden utilities/abandoned systems; above-ceiling surprises.
  • Hazmat indicators (asbestos, LBP, PCB, mercury, silica); sampling status and scope owner.
🔍 Walk the job with photos and mark-ups. Field truth > drawing intent—price what’s real.

⏱ Structural Risks & Demolition Sequencing

  • Demo order: finishes → ceilings → MEP → non-structural walls → structural cuts/picks → infills.
  • Sequence by phase/floor to maintain egress and operations for occupied buildings.
  • Schedule inspections (structural, fire) and protection resets between phases.
  • Stagger debris removal to avoid bottlenecks with other trades and keep lifts moving.

🧭 Cross-Reference Workflow & Sheet Index

  1. Start with A-Demo overall plan → identify rooms/zones/limits.
  2. Check S-Demo for structural notes, sawcut details, shoring, infill thickness.
  3. Open M/E/P Demo: find caps, equipment removals, reroutes, temp systems.
  4. Read General/Spec sections (hazmat, dust, noise, hours, disposal reporting).
  5. Log conflicts as RFIs with marked screenshots and sheet references.
Discipline Typical Sheets What to Confirm
A-DemoAD1.01–ADxRoom limits, keep/protect, partitions/ceilings/doors/windows.
S-DemoSD1.01–SDxShoring, sawcuts, openings, infill details, picks.
M/E/P DemoMD/ED/PDCaps, removals, temp systems, life-safety impairments.

✍️ Suggested Clarifications (copy/paste)

  • Demo limits per A-Demo; structural per S-Demo; M/E/P per respective demo sheets. Conflicts priced as alternates.
  • Disconnects/caps by licensed trades; demo to commence after written confirmation of shutoffs.
  • Phasing/night work premiums included only where noted; additional premium billed as T&M.
  • Temp partitions/negative air/infection control included per plan notes; additional zones are a unit price.
  • As-built deviations and unforeseen utilities handled by documented CO process.