Services all contractors need since 2010

Construction Law

Construction Law Cases

 

Construction Law Opinions

The Construction Law Podcast

 
 

Nygard v. City of Orono, No. 21-2941 (8th Cir. 2022)

After Nygard removed his driveway and was about to pour a new one, an Orono inspector told Nygard that he needed a permit. The next day, Nygard finished the driveway and applied for a permit. The new driveway was narrower than the previous one. The city responded with a form, imposing several conditions. Nygard crossed out some conditions, initialed the modified form, and returned it. After several exchanges, the city notified Nygard that he must agree to the conditions or “this matter will be turned over to the prosecuting attorney.” Nygard did not acknowledge the conditions. A police officer drafted a statement of probable cause, alleging that “work had been completed without having first obtained a permit” and listing some alleged deficiencies in its construction. According to the Nygards, the police did not inspect the property and some allegations were not true.

Nygard was acquitted of violating the city code. The Eighth Circuit affirmed the dismissal of his suit under 42 U.S.C. 1983, claiming the code was void for vagueness and alleging First Amendment retaliation, abuse of process, and malicious prosecution. Nygard’s prosecution was not based on falsehoods. The report did not claim that the conditions were required by the code but that Nygard had not agreed to the conditions and had replaced a driveway without a permit. Any failure to investigate did not defeat probable cause; the city already knew that he installed a driveway without a permit

 

Borst Brothers Construction, Inc. v. Finance of America Commercial, LLC

The Supreme Court affirmed the decision of the court of appeals and the district court on the questions of lien validity and priority in this mechanics' lien case, holding that there was no error.

Law requires that general contractors and owner-builders post a notice of commencement of work to Iowa's centralized, internet-based registry for mechanics' liens within ten days of starting work on a residential construction project. In the instant case, the owner-builder did not post notices of commencement on the registry for the five residential lots that it was developing, but two subcontractors did so several months after construction had begun. When the project went into default, a priority dispute arose between the two subcontractors and the project's commercial lender. The district court and court of appeals found for the subcontractors. The Supreme Court affirmed, holding (1) Iowa Code 572.13 did not change the principle that mechanics' liens will, in some circumstances, have priority over previously-recorded mortgages; and (2) the ten-day deadline for posting the notice of commencement to the registry applies to general contractors and owner-builders but not to subcontractors.

Areas of Law: Civil Rights, Constitutional Law, Construction Law, Government & Administrative Law, Zoning, Planning & Land Use

The Sixth Circuit affirmed the order of the district court granting summary judgment in favor of the City of Powell, Ohio and dismissing Golf Village North LLC's claims brought under 28 U.S.C. 1983 for violating its procedural and substantive due process rights, holding that there was no error.

Golf Village, a developer, sought to build a "residential hotel" on its property in Powell, Ohio but never filed the required zoning application. Instead, Golf Village requested that the City confirm the residential hotel was a permitted use of the property. The City directed Golf Village to file an appropriate application for "zoning Certificate approval" to receive an answer. Rather than reply, Golf Village sued the City. The district court granted summary judgment for the City. The Sixth Circuit affirmed, holding that Golf Village's procedural due process and substantive due process rights were not violated in this case.

Ries v. JM Custom Homes

GC Liability. Areas of Law: Construction Law, Labor & Employment Law, Personal Injury.

Court: South Dakota Supreme Court

Citation: LLC, 2022 S.D. 52

Opinion Date: August 24, 2022

Judge: Myren

Areas of Law: Construction Law, Labor & Employment Law, Personal Injury

The Supreme Court affirmed the decision of the circuit court granting summary judgment in favor of a general contractor based on the general contractor's statutory immunity under S.D. Codified Laws 62-3-10, holding that the circuit court properly concluded that workers' compensation was the sole remedy available to Appellant.

Plaintiff received a work-related injury at a construction site where his employer was a subcontractor. Plaintiff received workers' compensation benefits from his employer and then filed a negligence claim against the construction project's general contractor. The general contract subsequently amended its answer to assert statutory immunity under section 62-3-10. The circuit court granted summary judgment for the general contractor, concluding that the general contractor remained potentially liable for workers' compensation under S.D. Codified Laws 62-3-10 and, because of the exclusivity provisions of section 62-3-2, workers' compensation was Plaintiff's sole remedy. The Supreme Court affirmed, holding that the circuit court did not err in granting summary judgment for JM.

Porter v. Knife River, Inc.

Court: Nebraska Supreme Court

Citation: 310 Neb. 946

Opinion Date: February 18, 2022

Judge: Lindsey Miller-Lerman

Areas of Law: Construction Law, Personal Injury

The Supreme Court affirmed the order of the district court that granted summary judgment in favor of highway construction contractors and subcontractors (collectively, contractors) in this action alleging negligent maintenance of a construction site, holding that the contractors were entitled to summary judgment. Officer Curtis Blackbird died on duty when his police cruiser crashed into a parked crane and a portion of Highway 94 that was closed for construction. Plaintiff brought this action against the contractors, alleging negligence. The district court granted summary judgment for the contractors. The Supreme Court affirmed, holding that there was no triable issue of fact, and therefore, the district court properly granted summary judgment in favor of the contractors.

Pavlicek v. American Steel Systems, Inc. et al.

Court: North Dakota Supreme Court

Citation: 2022 ND 35

Opinion Date: February 18, 2022

Judge: Daniel J. Crothers

Areas of Law: Construction Law, Contracts, Insurance Law

Grinnell Mutual Reinsurance Company appealed a district court judgment ordering it to pay Larry Pavlicek $214,045.55 under a commercial general liability insurance (CGL) policy Grinnell had with JRC Construction. Grinnell argued the district court misinterpreted the insurance policy, and that it was not required to indemnify JRC Construction because its work product was defective. In 2013, Pavlicek hired a contractor to construct a steel building on his property. JRC Construction installed the concrete floor and floor drain for the project. Another subcontractor installed the in-floor heating system for the concrete floor.

After JRC completed the floor drain, it failed to properly install the concrete floor, and its attempts to repair the concrete damaged the drain. Pavlicek sued JRC for breach of contract relating to the defective work. In February 2020, Pavlicek filed a supplemental complaint against Grinnell, alleging it was required to satisfy the judgment as JRC’s insurer. Grinnell claimed it had no obligation to indemnify JRC under the CGL policy. The district court concluded JRC’s defective work on the concrete floor was not covered under the CGL policy, but damage to the floor drain was covered. Because removal and replacement of the floor and in-floor heat were necessary to repair the drain the court concluded the CGL policy covered all of those costs.

The North Dakota Supreme Court found that although the CGL policy provided coverage to repair the floor drain, it did not cover the cost of replacing the concrete floor because that damage was the result of JRC’s defective work. The district court erred in finding the CGL policy covered the entire concrete floor replacement because replacement of the floor was the only way to repair the floor drain. Further, the Supreme Court found the district court erred in concluding the CGL policy provided coverage for replacement or repair of the in-floor heating system beyond that which may be necessary to repair the drain.