Plumbing Estimating Class

📋 Module 8: Project Management & Change Orders

Keep scope, schedule, and cost under control. Run RFIs and submittals, protect margin with airtight change management, and communicate clearly from kickoff to closeout.

📘 Overview

This module connects estimating to execution. You’ll set up a PM toolkit (logs, dashboards, meetings), manage submittals/RFIs, control budgets and production, and price change orders (T&M and Lump Sum) with the right sequence: Direct Cost → Overhead → Profit (margin). Finish with a bulletproof closeout plan that accelerates payment.

🎯 Learning Objectives

  • Build a project startup packet: submittal register, RFI log, responsibility matrix, schedule.
  • Track cost and production weekly; forecast ETC (estimate-to-complete) by cost code.
  • Run a disciplined change process: notice, pricing, documentation, approval, tracking.
  • Price change orders correctly using markup vs. margin rules and CO impact costs.
  • Prepare clean pay apps and a closeout checklist to accelerate final payment.

Project Startup Essentials

  • Submittal Register: fixtures, valves, pipe/insulation, specialties, O&M.
  • RFI Log: conflicts, missing dims, spec ambiguities, shutdown windows.
  • Responsibility Matrix: sleeves, firestopping, patch/paint, controls.
  • Look-Ahead Schedule: 3–6 weeks with material/crew needs.

Cost & Production Tracking

  • Weekly hours by cost code; earned vs. planned quantities.
  • Labor curve vs. baseline; identify slippage early.
  • Commitments log (POs/subs) vs. budget; track remaining to buy.
  • ETC/EAC forecasting with variance notes.

Submittals & RFIs

  • Submit long-leads first (fixtures, specialty valves, equipment).
  • RFI within 24–48 hours of discovery; include sketch/marked-up plan.
  • Track due dates; escalate politely before impact dates.

Meetings & Communication Cadence

  • Weekly coordination: clashes, shutdowns, hold points, inspections.
  • Daily huddles: crew goals, constraints, material readiness.
  • Distribution: minutes with decisions, owners, and action owners/dates.

🔄 Change Order (CO) Workflow

  1. Notice: Written notification per contract (often 3–7 days) with brief impact statement.
  2. Field Documentation: photos, marked plans, timecards, delivery tickets, T&M tags.
  3. Pricing: Use DC → OH → Profit with clear breakouts; attach vendor quotes.
  4. Submission: Follow owner/GC form; include schedule impact and unit prices if requested.
  5. Approval: Do not proceed without written approval unless emergency protocol exists.
  6. Tracking: Log CO status (Proposed/Approved/Executed/Billed/Paid).

Lump Sum CO Pricing (Margin Target)

Use margin when you have a target price outcome:

DC = Labor + Materials (landed) + Equipment + Subs
Subtotal = DC × (1 + OH%)
CO Price = Subtotal ÷ (1 − Margin%)
Add: Schedule/Access Impacts (if permitted)

Example: DC=$8,000; OH=12%; Margin=12% → Subtotal=$8,960 → CO=$10,182

T&M CO Pricing (Contractor Rates)

Follow contract multipliers and approved rates:

CO = (Hours × Rate) + (Materials × (1 + Mat Mkup%))
   + Equipment/Small Tools + Subcontract + (OH/Profit as allowed)
Attach daily T&M tickets signed by site rep.

Tip: Keep T&M tickets legible, with names, hours by class, and scope description.

Pay Applications

  • Schedule of Values ties to bid/cost codes; update percent complete.
  • Include COs on separate lines with executed docs.
  • Attach certified payroll/waivers if required.
  • Resolve punch items promptly to release retainage.

Closeout Readiness

  • As-builts, O&M manuals, warranties, training signoffs.
  • Test/flush reports, disinfection certificates.
  • Final lien releases from suppliers and subs.
  • Turnover binder + digital archive (PDF + CSV exports).

📂 Module 8 Downloads & Templates

Copy from the blocks below and save as CSV/TXT to use in your sheets or PM software.

📦 Submittal Register (CSV)

Spec Section,Item,Required?,Submitted,Returned,Approved,Lead (days),Notes
22 40 00,Valves,,,No,,,, 
22 07 00,Pipe Insulation,,,No,,,, 
22 47 00,Grease Interceptor,,,No,,,, 
22 30 00,Plumbing Equipment,,,No,,,, 

❓ RFI Log (CSV)

RFI #,Subject,Submitted,GC/AE Due,Status,Impact (Cost/Sched),Response Ref,Notes
001,Conflicting DWV slope detail, , ,Open,Schedule,, 
002,Sleeve responsibility at Area B, , ,Open,Cost,, 

🔄 Change Order Log (CSV)

CO #,Title,Status,DC $,OH %,Margin %,Price $,Submitted,Approved,Billed,Paid,Notes
P-001,Add floor drains @ Restrooms,Proposed,,,,,,,,
P-002,Replace fixtures to Spec B,Approved,,,,,,,,

📝 T&M Ticket Template (Copy/Paste)

Project:
Date/Time Window:
Scope of Extra Work:
Crew (Name/Class/Hours):
Materials (Qty/UoM/Desc):
Equipment (Type/Hours):
GC/Owner On-Site Rep (Print/Sign/Time):

📊 Weekly Cost Report (CSV)

Cost Code,Desc,Budget $,Committed $,To-Date $,ETC $,EAC $,Variance $
15-100,Pipe Rough-In, , , , , , 
15-110,Fittings/Valves, , , , , , 
15-200,Fixtures/Trim, , , , , , 

💵 Pay App Checklist (TXT)

• Updated SOV; percent complete by line
• Executed COs attached
• Stored material tickets (if allowed)
• Lien waivers (sub-tier as required)
• Certified payroll if prevailing wage
• Updated schedule narrative (if required)

🗓 Coordination Meeting Agenda (TXT)

1) Safety & access constraints
2) RFIs status & urgent decisions
3) Submittal/approvals & long-leads
4) Look-ahead (3–6 weeks) by area
5) Foreman needs (manpower/material)
6) Shutdowns/inspections
7) COs & potential changes
8) Action items (owner & due date)

🧪 Practice Exercise (45–60 min)

  1. Populate the Submittal Register and RFI Log from a sample set of plans/specs.
  2. Build a Change Order for a spec change (include quotes, DC→OH→Margin math).
  3. Enter weekly hours/quantities into the Cost Report and forecast ETC/EAC.
  4. Draft a Pay App Checklist for this month’s billing and attach supporting docs.

👩‍🏫 Teacher Notes (Facilitation Guide)

  • Mini-lesson (10 min): CO math—show markup vs. margin with a live example.
  • Workshop (25 min): Teams price one Lump Sum CO and one T&M CO; attach T&M ticket.
  • Apply (10–15 min): Fill RFI log and draft one clear RFI with a sketch/narrative.
  • Debrief (5 min): Share top three practices that speed approvals and cash flow.