Demo Estimating — Module 7

Creating the Final Demolition Estimate

Assemble a clear, defensible number. Map your costs to the bid form, level quotes, run QA/QC, and package a professional submission that wins work and protects scope.

🎯 Learning Objectives

  • Build a complete cost summary (labor, equipment, disposal, temp facilities, safety, OH, contingency, margin).
  • Level supplier/subcontractor quotes and document basis of selection.
  • Map totals to the client’s bid form, including alternates, unit prices, and addenda.
  • Run a QA/QC math audit, benchmark review, and risk check before submission.
  • Prepare a clean submission package with clarifications, inclusions/exclusions, and signatures.

🧱 Itemize All Cost Buckets

  • Labor: crew mix, hours, rates, shift premiums, OT assumptions.
  • Equipment: excavators/skids, saws, lifts, fuel, delivery/pickup, operator rates.
  • Disposal: dumpsters/hauls, tipping (ton/yard), recycling credits, manifests.
  • Materials/Protection: fencing, barriers, poly, negative air, temp lighting.
  • Temp Facilities & Safety: restrooms, handwash, site lighting, guards, PPE, monitoring.
  • Permits/Fees: demo permit, street use, lane closure, utility disconnects.
  • Overhead: recovered per your policy (rate or %).
  • Contingency: sized by risk register (see Mod 6).
  • Profit (margin): target based on risk/market; compute from price, not cost.
🧾 Pro Tip: Keep alternates, allowances, and unit prices outside your base number for clarity.

📋 Sample Cost Summary (Excerpt)

Category Cost ($) Notes
Labor84,6003-person crew, 6 weeks, no OT
Equipment41,9002 swaps, operator included
Disposal52,300tipping at $120/ton, 8 hauls
Temp Facilities/Safety9,750fence, restrooms, NA units
Permits/Fees6,200demo permit + traffic control
Overhead21,500policy 12% on DC+Cont
Contingency18,400EMV x 1.2 buffer
Cost+OH+Cont234,650before profit
Selling Price (18% margin)286,158price = Cost ÷ (1−margin)

*Replace with your actual numbers. Example shows flow, not required rates.

🔍 Vendor/Subcontractor Quote Leveling

Normalize scope, terms, and lead times before selecting the preferred vendor.

Scope Package Vendor A Vendor B Vendor C Notes/Gaps
Dumpsters & Hauls$18,600$17,900$19,250B excludes ton overage
Negative Air/Containment$7,200$7,650$6,950A includes filters/NA readings
Traffic Control$5,800$5,200$5,400B excludes police details
Document selection basis (price, scope completeness, schedule, performance history).

🗂 Map to Client Bid Form

Use the owner’s divisions/sections and reconcile to your internal summary.

Bid Form Line Our Category Amount ($) Notes
01: Selective DemoLabor + Small Tools84,600see takeoff tab
02: EquipmentExcavators/Lifts41,900incl. delivery
03: Hauling/DisposalDumpsters/Tipping52,300MRF + landfill
04: Temp/SafetyFacilities/Safety9,750fence, NA units
Total (must = base price) 286,158reconciled

✍️ Clarifications, Inclusions & Exclusions (Copy/Paste)

  • Includes legal disposal at licensed facilities; diversion receipts and weight tickets provided at closeout.
  • Traffic control, lane closures, and police details priced per allowance; overages billed at actuals.
  • Abatement (lead/asbestos) excluded unless specifically noted; work requires negative air/containment by others or as alternate.
  • Work during normal hours; off-hours premiums by alternate.
  • Owner to provide access, power, water, and staging unless specified.

🧪 Final QA/QC Checklist

  • ✅ Math audit (sum of lines = category totals = bid form total).
  • ✅ Vendor quotes leveled; backup attached with quote numbers & dates.
  • ✅ Addenda acknowledged; RFIs incorporated.
  • ✅ Benchmarks checked (e.g., $/SF demo, $/CY concrete, $/ton disposal) vs history.
  • ✅ Risk register reviewed; contingency aligns with EMV; alternates and allowances separated.
  • ✅ Submission package complete (cover letter, bid form, clarifications, schedule notes).

📦 Submission Package Contents

  • Signed bid form with base price, alternates, unit prices, addenda acknowledgments.
  • One-page cover letter summarizing scope, schedule, and assumptions.
  • Clarifications, inclusions/exclusions, allowances list.
  • Required attachments (W-9, COI, bonds if specified, safety plan excerpt, recycling plan).