The HVAC Study Module 5
👷 Module 5: Labor & Crew Productivity
Labor is your biggest risk — learn to turn baseline units into field-realistic hours with transparent factors, smart crew planning, and finish-date math.
HVAC Estimating & Plan Reading CourseOverview
Use baseline manhour (MH) units (from SMACNA/MCAA/PHCC or company standards) as your starting point, then apply documented productivity factors for height, congestion, access, schedule pressure, and conditions. Convert total hours into a crew plan with realistic throughput, and understand how overtime and learning curves affect cost and duration.
🎯 Learning Objectives
- Pull defensible MH units from guides and historicals and keep them version-controlled.
- Build a composite productivity factor (multiplicative) instead of guessing a single adder.
- Translate hours into crew size, duration, and weekly goals — with float and inspections.
- Evaluate the tradeoff of overtime: faster calendar vs. higher cost and lower productivity.
- Model learning curves for repetitive scopes (e.g., VAVs, FCUs) to sharpen totals.
📚 Sources for Labor Units
- SMACNA ductwork install tables (airside).
- MCAA / PHCC labor guides (piping/equipment).
- Company historicals (closed jobs w/ actuals) and superintendent feedback.
📏 Baseline Manhour Units (Examples — replace with your standards)
Airside
Item | Unit | MH/Unit |
---|---|---|
Rect duct 24×12 (CL2) | LF | 0.25 |
Spiral Ø18 | LF | 0.20 |
Elbow 90° (med) | EA | 0.80 |
Transition (rect-rect) | EA | 1.20 |
Volume damper | EA | 0.70 |
Wet/Equipment/Controls
Item | Unit | MH/Unit |
---|---|---|
CHWS 2" (std) | LF | 0.30 |
Valve install 2" | EA | 1.10 |
VAV box (w/ reheat) | EA | 6.00 |
RTU set (excl. crane) | EA | 10.00 |
DDC point (avg) | EA | 0.40 |
🧮 Productivity Factor Library (Typical Ranges)
Condition | Typical Factor | Notes |
---|---|---|
Work height 12–20 ft | ×1.10 – ×1.25 | Lifts, staging, fall protection |
Congested ceilings/MEP clash | ×1.10 – ×1.30 | Rework risk & short cuts |
Occupied/night work | ×1.15 – ×1.30 | Access windows, protection, escorts |
Seismic bracing spec | ×1.05 – ×1.15 | Extra hardware & layout |
Weather (heat/cold/wind) | ×1.05 – ×1.20 | Outdoor/roof scope |
Security/badging | ×1.03 – ×1.10 | Check-in time loss |
Accelerated schedule | ×1.05 – ×1.15 | Stacked trades/overtime drag |
🧠 Formula — From Units to Crew Plan
Total Hours = Σ( Quantity × MH/Unit ) × CompositeFactor + Supervision + Access/Setup
Duration (workdays) = Total Hours ÷ (Crew Size × Hours/Day) → add Float & Inspection days
🧰 Mini Tools
🧮 Composite Factor Builder
Composite Factor: —
Multiply factors (not add). Document the “why” in your notes.
⏱️ Task Labor Calculator
Total Labor Hours: —
Replace units with your standards; keep supervision/setup separate.
👥 Crew Planner & Finish Date
Effective Crew Hours/Day: —
Workdays Needed: — | Weeks: —
Finish date shown if start date is provided.
⏳ Overtime Cost & Derate
Avg Cost/hr (loaded): —
Effective Hours vs. 40: —
OT can shorten the calendar but raise $/installed-hour.
📉 Learning Curve (Wright’s)
Modeled Total Hours: —
Unit time model: Tₙ = T₁ · nᵇ, where b = log(r)/log(2). Sums units 1…N.
📋 Field-Ready Labor Breakdown (Template)
Area/Scope | Baseline Hrs | Composite Factor | Adj. Hrs | Crew | Days | Notes |
---|---|---|---|---|---|---|
L2 SA Main | 50 | 1.15 | 57.5 | 2J+1A | 3.0 | Lifts; night access |
VAV Set (x6) | 36 | 0.92* | 33.1 | 1J+1A | 2.2 | *85% learning curve |
Roof RTU set | 12 | 1.10 | 13.2 | 2J | 1.0 | Crane, weather risk |
🧪 QA/QC — Before You Publish Hours
- Units sourced & dated; no mixing different baselines.
- Factors listed with rationale (height, congestion, schedule, weather, security).
- Supervision, access/setup, travel, and inspections explicitly shown.
- Crew plan math reconciles to total hours and calendar.
- OT decisions documented (cost/benefit), learning curve applied where repetitive.
- Versioned export saved (e.g., 2025-02-Module5_LaborPlan_V03.xlsx).
🧠 Practice & Exit Ticket
- Compute total hours for 200 LF rect 24×12 @0.25, 12 El90 @0.80, 6 transitions @1.20 with a 1.15 composite, +14 hrs overhead.
- Plan crew with 2J+1A (A=0.75 of J), 8 h/day, 5 d/wk; show days and weeks; if start next Monday, what’s the finish date?
- Evaluate OT at 60 hrs/wk with 10% derate and 1.5× pay — what’s the loaded $/hr and effective hours vs. straight time?
- Model learning curve for 20 VAVs: T₁=6.0 hrs, 85% rate. Compare to “no learning” total and comment on the delta.