Learn the Basics of Demo Plan Reading & Estimating

1. Understanding Demo Plans

  • A Sheets: Look for “Demolition” notes or layers (existing to be removed).
  • Demo Legends: Dashed lines or hatch patterns showing removed walls, ceilings, etc.
  • Mechanical/Electrical Plans: Indicate equipment, ducts, conduit to be demoed.
  • Scope Notes: Read general demolition notes and keyplan callouts carefully.
Use different colors to identify wall, floor, ceiling, and utility demolition areas!

2. Takeoff Basics

  • Count and measure all removals: walls (LF), ceiling (SF), fixtures (each).
  • Document haul-off requirements (demo + debris).
  • Include patching or prep for following trades.
  • Separate selective, total, and structural demo scopes.
Note all sawcutting, slab removal, or hazardous material areas!

3. Manhour & Labor Estimating

  • Wall Demo: ~0.2–0.3 hr/LF
  • Ceiling Demo: ~0.1–0.2 hr/SF
  • Fixture/Equipment Demo: ~0.5–1.0 hr/each
  • Haul-Off & Dump Fees: Calculate by yard or ton
Add crew hours for loading, transport, and safety procedures!

4. Building the Estimate

  • Labor Cost: Based on total hours × demo rate (e.g., $55/hr)
  • Debris Cost: Estimate dumpster rental and tonnage fees
  • Overhead & Profit: Add markup (typ. 15–25%)
  • Special Conditions: Factor in permits, night work, containment
Use a checklist to make sure all required patching and prep is included!