Demo - Module 4

Demo Module 4

Demo Estimating — Module 4

Labor Estimating & Equipment Selection

Labor drives demo cost. In this module, translate production into hours, pick the right machines and attachments, and model schedule/shift decisions—without eroding safety or margin.

🎯 Learning Objectives

  • Build a burdened labor rate and convert production into crew-hours and duration.
  • Apply productivity factors (height, access, congestion, occupied/ICRA, weather).
  • Select equipment & attachments that maximize safe production.
  • Compare manual vs. mechanical approaches and find the break-even point.
  • Quantify shift/OT and load-out logistics impacts on cost and schedule.

💼 Estimating Labor Costs

Start with hours (not dollars). Multiply a defendable production rate by real conditions, then price with a burdened rate.

  • Sources: your historicals, timecards, vendor production sheets, RSMeans/NECA/SMACNA (as ROM only).
  • Burdened Rate: wage + taxes + benefits + comp + small tools + supervision allocation.
  • Scheduling: night work, phasing resets, inspection windows → add time or premium.
  • Traceability: log sheet & area tags for each rate. If challenged, you can show your math.
🧠 Tip: Price disconnects, safety, and protection as explicit lines. Don’t hide them in production.

🤝 Union vs. Non-Union Considerations

  • Union/Prevailing Wage: higher wage & burden; predictable classifications; certified payroll admin.
  • Open Shop: flexible assignments; verify training for saws, torching, rigging, silica plans.
  • Public/Urban work: often mandates prevailing wage & specific ratios/dispatch rules.
  • Subcontracts: align bid with labor expectations and include escalation clauses where allowed.
📋 Transparency: Some owners require hours & classifications by task—prep a summary export.

📊 Productivity Factors & Ranges (guide)

Factor Typical Impact Notes
Height (10–20 ft)+15–35% hoursLifts, tie-offs, spotters, drop protection.
Tight Access / Congestion+10–40%Material handling & shared trade space.
Occupied / ICRA+15–50%Barriers, negative air, cleaning resets.
Night/Off-Hours+10–25% + premiumsLower support, logistics constraints.
Material Hardness+0–50%e.g., heavily reinforced concrete, epoxy floors.

🚜 Equipment Selection & Attachments

Pick the smallest machine that safely achieves the rate—then add attachments that unlock productivity.

  • Excavators: shear (steel), breaker/hammer (slab/footings), pulverizer (concrete processing).
  • Skids/CTLs: tight interior load-out, grapple buckets for debris sorting.
  • Robotics: remote hammers for elevated slabs or high-risk spaces.
  • Lifts: scissor/boom for above-ceiling demo and façade removals.
  • Support: buggies, dumpsters, conveyors, debris chutes for vertical moves.
Include: rental days, delivery/pickup, operator, fuel, wear parts (blades/bits), spotters/riggers, daily inspections.

⚖️ Manual vs. Machine-Assisted Cost Comparison

  • Manual: best for selective interiors, delicate salvage, low-volume removals; higher crew-hours.
  • Mechanical: best for structural and bulk debris; adds rental/fuel/operator but slashes hours.
  • Break-Even: choose the path with the lower total cost at your required duration/risk.

🛡️ Safety, Compliance & Supervision (Don’t Bury It)

  • Spotters/flaggers, LOTO, daily JHAs, silica controls & water, debris chute attendants.
  • Supervisor/foreman planning time and inspections—budget real hours.
  • ICRA resets, negative air checks, final cleaning between phases.

👥 Sample Crew & Rate Sheet (ROM)

Role / Equipment Burdened Rate Notes
Demo Laborer$XX/hrSilica compliance, barriers, load-out.
Operator (Excavator)$XX/hrRigging & safety checks.
Foreman/Superintendent$XX/hrPlanning & inspections.
Excavator + Breaker (Rental)$XXX/dayPlus fuel & delivery/pickup.
Skid Steer + Grapple$XXX/dayInterior load-out.

✍️ Suggested Clarifications (copy/paste)

  • Rates assume access per plans; height above 12' and night work carry listed productivity premiums.
  • Equipment includes rental days noted; additional days billed at published daily rates.
  • Spotters, LOTO, silica controls, negative air resets included as separate line items.
  • Owner/GC to provide shutdown confirmations before demo start; delays beyond control are change order eligible.

🧰 Labor & Equipment Mini Tools

💳 Burdened Labor Rate
⏱️ Crew Duration Planner
📏 Height & Access Factors
⚖️ Manual vs Machine Break-Even
🧱 Equipment Cost Builder
🚚 Load-Out Cycle Time

*Replace ROM factors and dollar values with your company’s actual rates and historic production.