Services all contractors need since 2010

Demo Cheat Sheet

Demo Cheat Sheet

Demo Contractor • Cheat Sheet

🏗️ Field & Estimating Cheat Sheet

Fast tips, formulas, mini-tools, and templates for daily use—pre-bid through closeout.

🧭 Pre-Bid Quick Wins

  • Mirror the client’s bid format (divisions/sections). If unsure, ask for the bid form early.
  • Log addenda in a simple table (number, date, summary) and reissue your QTO with a revision stamp.
  • Chase two quotes for major scopes (e.g., lighting/switchgear, HVAC, finishes). Scope-complete beats lowest number.
  • Document assumptions in-line while estimating—those become clarifications later.
  • Benchmark sanity: compare $/SF or $/room to 2–3 similar projects (flag ±15% variance).

📐 Takeoff & Pricing Tips

  • Calibrate every sheet on a known dimension; avoid “apply to all” unless verified on 2+ dims.
  • Separate layers: Demo / New / Alternates / Allowances. Prevent double-counts on exports.
  • Keep QTO exports tidy: Area • Item • Qty • Unit • Rev • Notes.
  • Use unit pricing where possible (LF/SF/EA). Bag small tools, freight, permits as consistent lines.
  • Update vendor quotes to the very end—track timestamp and lead time on your leveling sheet.

🧮 Mini Calculators

Margin ↔ Markup

Markup: • Mult:
Formulas: Markup = m/(1−m); Margin = u/(1+u)

Crew Duration (Days)

Duration:

Fast Cost Impact

Price: • Profit:

✉️ Rapid RFI & Email Subjects

RFI-__: Question: [State the specific conflict or missing info in one sentence.] Impact: [Schedule/cost/coordination risk if unanswered.] Request: [Exact detail needed or proposed resolution.] Needed by: [Date/Time] to maintain schedule.
Subjects
  • RFI-12 – Plan conflict E2.3 vs E7.1 – Conduit routing
  • Submittal – Lighting Package – Rev B – Lead Times Included
  • Bid Submission – – Div 01–33 – Demo Contractor

🔄 Change Orders — 6 Moves

  1. Log request (date/source); assign CO#.
  2. Clarify scope in writing (drawings/spec refs).
  3. Quantify labor/material/equip + productivity hits.
  4. Apply correct stack: DC → OH → Profit (margin).
  5. Identify schedule impact & material lead times.
  6. Submit with expires-on date + backup exhibits.

Tip: Use unit prices where available to accelerate approvals.

🛠️ Daily Field Controls

  • AM huddle: risks, deliveries, outages, inspections.
  • Daily JHA & photos: before/during/after work areas.
  • Three constraints cleared daily (info, material, access).
  • 2:00 PM look-ahead: tomorrow’s crew & laydown ready.

📦 Procurement Lead-Times (Example)

ItemTypical LeadNotes
Switchgear / Panels14–24 weeksConfirm at bid; consider VE alternates
Lighting Fixtures4–10 weeksWatch custom finishes & controls
Mechanical RTUs10–20 weeksEarly submittal critical path
Doors/Frames/Hardware4–8 weeksCoordinate fire ratings & hardware sets

Action: Release long-leads within 5 business days of award with approved submittals.

🧪 QA/QC — Last Look

  • Quantities reconcile to drawings/spec sections.
  • Math audit: random-line check + totals check.
  • Compare against $/SF benchmarks (±10–15%).
  • Lead-time risks called out; alternates separated.

📁 Closeout Essentials

  • O&M manuals, warranties, as-builts, training dates.
  • Punchlist log with photo proof of completion.
  • Final lien releases & permits/CO documents.
  • Lessons learned captured (schedule/cost/RFIs).